Sunday 1 April 2012

Time frame....for Leeson Park Avenue

Just a quick post to up date you on the time frame for the rest of the build.

May, Wk 1 & 2
Building will be completely closed in
Glass floor will be fitted
Cornice and covings will be fully fitted
Hot Tub will be installed
Underfloor heating will be installed in the downstairs and then the concrete flooring will be poured
The back of the house will be externally glad with corten steel

May, Wk 3 & 4
Decorators will come in to finish the house
External works will be completed (decking, planting, benches, landscaping)

The Dean Cooper  Design Kitchen and bathrooms will then be fitted!

Hopefully we will be moving in to the house in the first week or two of June.  Fingers crossed!!!!

                         Wallpaper Samples from Laura Ashley!

No comments:

Post a Comment

I love to read comments! Let me know what you think