Sunday 16 October 2011

A new design for the front room!

Open plan front room, with a view back up to higher entrance hallway, which utilises the high floor to ceiling height space   The main feature of this space will be a built in wrap around seating area under the window and shutter boxes.


Here is a photo of me standing in the front room and how it currently looks!


                                                                Back garden

Sunday 9 October 2011

Scary scenes in LPA!

Not having visited the site for a few weeks I was quite shocked with what I saw this weekend.  Although I had been warned by Ciaran that buildings get a lot worse looking before they get better, I was really quite shocked by the level of destruction that needs to happen in order for a house to be restored.  Everything needs to be stripped right back and made good to ensure that the structure is safe.  At this point it can then be built back up.  Not having lived in this house, I can depersonalise and distance myself from the works, but, I think if I had lived here and then moved out in order for building works to commence, I would be very upset seeing the house in the current state.
Luckily I have Ciaran with me at every visit and he talks me through everything - why things have to be done they way they are at this point, etc.  He also reminds me of what it will be like when it is finished.  Likening building to cooking he says "You can't make an omelette without breaking eggs"!!!!


                                           Internal walls are all removed.

                    This where the Hot Tub is going to be positioned!

 Master bedroom with the ceiling removed - roof will come off shortly.....

 Looking out from the back room to where the new extension will be built.

                                                            What's left of the hallway!



Wednesday 5 October 2011

Timber Floor has been taken up



Removed and stored the existing timber floor of the front room and hallway.  Dug out the subsoil and poured the ground floor slab to the sub slab in the main house.  We also tanked the existing walls and made them water tight.


Internal walls have all been removed at this stage.


The existing stairs remains until we can figure out how to dismantle it and then we need to find a place to store it until we can put it back in to place.