Bricks to the front of the house have been cleaned and repointed. Ciaran specified that tuck pointing should be used on the pointing - when you get up close to the pointing you can see an indented line all the way around the pointing - an element that might be missed but as Architect Mies Van Der Rohe said "God is in the details"
The back wall has been cleaned down and repointed - Ciaran has made it a feature of the house with the back wall being made of glass and built right up to this natural stone wall. I think it is one of his favourite things in the house!
We are nearing the end of the main building works - lists of what has to be done in each room have been put up on the plastered walls.
Some of our new lights ready for fitting in the bathroom
Current state of the bathroom
This blog was originally started to track our progress as we regenerated a derelict Victorian house in Dublin. We turned an old crumbling ruin in to our dream house! If you wish to read through the trials and tribulations of the house build it is best to start at the oldest blog post and read in date order. The blog then evolved in to being all about my life in Dublin, Ireland and then life in Malaga, Spain with artist "PIGSY" and now back in Dublin I hope you enjoy reading it!
Sunday, 11 March 2012
Thursday, 8 March 2012
Plaster mouldings!
Ciaran visited the plaster moulding factory in Wicklow yesterday to choose plaster coving, ceiling roses and mouldings for the house. He brought along some samples of the coving that was originally in the house so that he could replace like with like.
He bought new mouldings for the arch in the hallway, a few ceiling roses and some new coving for the downstairs of the house.
The company he went to for the plaster works use traditional methods to make the plaster mouldings and all of their designs are based on authentic designs contemporary to certain periods and regions.
He bought new mouldings for the arch in the hallway, a few ceiling roses and some new coving for the downstairs of the house.
The company he went to for the plaster works use traditional methods to make the plaster mouldings and all of their designs are based on authentic designs contemporary to certain periods and regions.
Sunday, 4 March 2012
Ready for plastering
Work on the house is progressing nicely. The place will be plastered tomorrow. The floor (untreated White American Oak) will be laid upstairs. Hopefully by the end of the week we will have the downstairs underfloor heating laid and then it will be ready for the big concrete pour!
Sunday, 26 February 2012
Itsa.....
Domini Kemp and her sister Peaches have opened a new restaurant!
Itsa...... RanelaghThe Mountaineer Bagel and the All Day Cure Bagel.
Short Americano. Mmmm!
ODKM Facebook
First fix in progress....
Front room
Glass roof!
Looking towards the back of the house - the kitchen will be positioned on the left hand side of the house.
Underfloor heating system being laid in the master bedroom.
Glass roof!
Looking towards the back of the house - the kitchen will be positioned on the left hand side of the house.
Wednesday, 22 February 2012
Look up!
The glass skylight to the studio was fitted today. I think this is a really unique element to the house. It gives the room at the top of the third landing an atrium feel to it.
I look forward to looking at the stars in the sky at night time and blue skies during the day!
I look forward to looking at the stars in the sky at night time and blue skies during the day!
Saturday, 18 February 2012
Master Bedroom
The master bedroom has been skimmed. The window boxes, coving and the fireplace will be refitted. This will re-inject the character back into this bedroom!!